Many AMC quotes are guesses with a spreadsheet around them. Someone takes last year's price, adds a bit, and hopes the contract does not turn into a loss.
A defensible price comes from inputs you can write down, a formula you can explain to a customer, and GST added at the end. This guide covers three methods, how comprehensive and non-comprehensive cover change the number, and one worked example.
What AMC charges have to cover
Whatever method you use, the annual charge has to pay for five things:
- Scheduled visits. The preventive maintenance visits you commit to in the contract.
- Breakdown calls. Unscheduled visits, which you can only estimate.
- Parts risk. What replacements are likely to cost, if the contract covers parts.
- Overhead. Administration, tools, travel and support that do not show up per visit.
- Margin. What is left after all of the above.
If your price does not clearly account for each of these, you are absorbing the missing one without knowing it.
Method A: cost-plus
Cost-plus builds the price from your own costs. It is the most transparent method and the easiest to defend.
Cost base = (expected visits x cost per visit)
+ (expected breakdown calls x cost per call)
+ parts and repair reserve
+ overhead
Base charge = cost base + margin
Total payable = base charge + GST at 18%The weak point is the estimate of breakdown calls and parts. Use your own service history, and revisit it each renewal.
Method B: percentage of asset value
Here the annual charge is a percentage of the installed value of the assets covered. It is quick, and it scales with the size of the estate.
Set the percentage from your own claim history: what you spent servicing and repairing comparable assets, divided by their value. This guide gives no industry percentage, because one "typical" figure hides differences in equipment age, usage and site conditions.
Method C: per visit or per unit
This suits non-comprehensive cover. You set a rate per asset, or per visit, and bill parts separately when they are used.
Base charge = (rate per asset x number of assets)
or (rate per visit x number of visits)
Total payable = base charge + GST at 18%It is simple to explain and keeps parts risk out of the price, but the customer cannot predict total spend.
Comprehensive vs non-comprehensive
The same asset prices differently depending on what the contract covers.
- Comprehensive cover includes parts. The price must carry a parts and repair reserve, so you are taking on the risk that a costly component fails.
- Non-comprehensive cover includes visits and labour only. Parts are billed as used, so the base charge is lower and the customer carries the parts risk.
Write the split into the contract wording, so nobody assumes a part is covered. For how covered and out-of-contract work is recorded against a contract, see AMC contract billing.
A worked example (illustrative numbers)
The company and figures below are fictional and rounded. They show the method, not a benchmark, and they are not a recommendation for what you should charge. Amounts are before GST unless a row says otherwise.
A services company is quoting an AMC for 40 office workstations for one year. Costs come from its own estimates.
| Item | Working | Comprehensive | Non-comprehensive |
|---|---|---|---|
| Scheduled visits | 4 visits x Rs 2,500 | Rs 10,000 | Rs 10,000 |
| Breakdown calls | 20 calls x Rs 1,000 | Rs 20,000 | Rs 20,000 |
| Parts and repair reserve | Estimated | Rs 30,000 | Nil (billed as used) |
| Overhead | Estimated | Rs 10,000 | Rs 10,000 |
| Cost base | Rs 70,000 | Rs 40,000 | |
| Margin at 20% of cost | Rs 14,000 | Rs 8,000 | |
| Base charge (before GST) | Rs 84,000 | Rs 48,000 | |
| GST at 18% (SAC 998713) | 18% of base charge | Rs 15,120 | Rs 8,640 |
| Total payable | Rs 99,120 | Rs 56,640 |
The comprehensive base charge works out to Rs 2,100 per workstation, and the non-comprehensive one to Rs 1,200. GST is added to each base charge as a separate line on the quote, here at 18% under SAC 998713 (maintenance and repair of computers and peripheral equipment). Confirm the classification and rate for your own contract with your tax adviser before quoting.
Adjusting the price
Once you have a base, three adjustments come up most often.
- Multi-year terms. A discount for a longer commitment is reasonable, but decide it deliberately.
- More or fewer visits. Each visit has a cost, so change the visit count and the price together.
- Renewal repricing. Price the next term from what the last one consumed: visits, breakdown calls, parts and margin. A contract that ran under its estimate can hold; one that ran over needs to move.
How a contract records it in DexVee
DexVee does not calculate an AMC price for you. You work out the charge with the method above and enter it. What DexVee does is keep the result and its consequences in one place.
- A contract holds the billing amount, billing frequency (monthly, quarterly, half-yearly, annual, one-time or custom), and start, end and renewal dates. The amount is whatever you enter, so decide whether your quotes and your contract records show it before or after GST, and use the same basis every time.
- Each contract carries a standard service price per work order, and work-order lines can be marked as covered, partially covered or out of contract.
- A contract performance report shows utilisation and margin, and an internal-only renewal outlook suggests a renewal price (shown excluding GST) that is hold or increase only, with the increase capped at 25 percent. It is a suggestion, and it is never applied automatically.
- Active contracts move to "expiring soon" 30 days before the end date.
Once the price is agreed, what an AMC invoice must show under GST covers the SAC code, the contract period and the coverage lines. See AMC contract billing, renewal tracking and maintenance scheduling. For the wider model, read the AMC-driven business model guide and AMC renewal automation. If you bill across several GST registrations, see the multi-GSTIN billing guide. The related solutions are finance and billing and field service management.