Most AMC contracts promise "quarterly preventive maintenance" in a single line. The engineer who turns up at the site needs a lot more than that: which assets, how often for each one, what to check, and what proof to leave behind. This page gives you a preventive maintenance schedule template you can copy straight into a spreadsheet, organised by asset class, frequency and checklist. It also has a blank schedule for tracking visits per contract, guidance on filling both in, and an honest description of how the same schedule runs inside a field service management system.
The template comes first. The explanation follows it.
The preventive maintenance schedule template
Each row is one asset class. Frequencies are illustrative defaults for the kind of IT, network, power and security equipment typically covered under an AMC. They are not drawn from any standard. Where the manufacturer's manual or your signed contract says something different, that wins.
| Asset class | Frequency | Checklist items (one action per line) | Evidence to capture | Owner / skill |
|---|---|---|---|---|
| Network switch / router | Quarterly | Check port and fan status LEDs; review system log for errors since last visit; confirm uplink and redundancy links are up; take a configuration backup; note firmware version | Config backup file name; firmware version; log extract if errors found | L2 network |
| Firewall / UTM | Monthly | Confirm licence and subscription validity; review threat and system logs; check HA status if paired; take a configuration backup; note firmware version against vendor advisories | Config backup; licence expiry date; firmware version | L2 security / OEM-certified |
| Wi-Fi access points and controller | Quarterly | Confirm all APs are online on the controller; review client and interference alerts; check mounting and cabling; note controller and AP firmware | Controller AP status screenshot; firmware version | L1 / L2 wireless |
| UPS / battery bank | Monthly | Check alarm panel and event log; record input/output voltage and load; inspect batteries for swelling, leakage or corrosion; clean vents and filters | Panel photo; voltage and load readings in the visit notes | L1 power |
| UPS / battery bank (deep check) | Half-yearly | Run a battery backup test under controlled conditions; check terminal tightness; review battery age against replacement interval | Backup test duration and result; battery install date | L2 power / OEM-certified |
| Server / storage | Quarterly | Check hardware health alerts (disks, PSU, fans); confirm backup jobs completed; review free capacity; clean dust from intakes | Health report export; backup job status; capacity figure | L2 systems |
| CCTV / NVR | Monthly | Confirm every camera is recording; check NVR disk health and retention days; clean camera lenses in reach; verify date and time sync | Retention days noted; list of offline cameras, if any | L1 security |
| Split / precision AC (server room) | Monthly | Clean or replace filters; check condensate drain; record supply and return temperature; check for unusual noise or vibration | Temperature readings in notes; filter photo | HVAC technician |
| DG set | Weekly | Check fuel, oil and coolant levels; check battery and charger; run no-load test as per site procedure; record running hours | Running hours; fuel level; test run logged | DG technician |
| Medical equipment (example: patient monitor) | As per OEM, often Half-yearly or Yearly | Run manufacturer self-test; inspect cables and probes; verify alarms; perform calibration or safety checks the OEM specifies | Self-test result; calibration record reference | OEM-certified biomedical |
How to read it: frequency is how often the asset gets a visit. The checklist is what the engineer ticks during that visit. Evidence is what goes into the service report or visit notes so you can prove the work was done. For one asset class (UPS) there are two rows, a monthly routine check and a half-yearly deep check. That pattern of a light, frequent row plus a heavier, rarer row is often cleaner than one long checklist that nobody finishes.
Blank schedule to copy
Use this second table to track individual visits per contract. One row per asset (or per asset group at a site).
| Contract no. | Site | Asset / serial | Asset class | Frequency | Last visit | Next due | Engineer | Status |
|---|---|---|---|---|---|---|---|---|
"Status" works best with a short fixed list: Scheduled, Done, Overdue, Skipped (with reason).
How to fill in the template for each AMC contract
Start from the contract's visit commitment, not the calendar
Open the signed AMC before you open the spreadsheet. The contract tells you how many preventive visits the customer is paying for, over what period, and for which equipment. If it says four PM visits a year for the network and twelve for the UPS, that is your minimum. A schedule built from the calendar ("we'll do everyone in the first week of each quarter") tends to drift away from what each customer actually signed for.
Set frequency per asset class, using the OEM manual as the floor
The manufacturer's recommended service interval is the floor, not the ceiling. If the OEM recommends a battery check every six months and the contract promises quarterly, schedule quarterly. If the contract promises yearly but the OEM recommends six-monthly, raise it with the customer rather than quietly under-servicing. Site conditions matter too: a dusty plant floor or a server room with marginal cooling may justify a shorter interval than an air-conditioned office.
Write checklist items an engineer can tick: one action per line
"Check UPS" cannot be verified. "Record UPS output voltage and load" can. Each line should be a single action with an obvious done or not-done state. If an item needs a reading, put the reading in the visit notes and keep the checklist line as the action ("Record input/output voltage"). Keep each checklist short enough to finish on a normal visit. Anything longer belongs in a separate, less frequent row.
Record the site, asset/serial and assigned engineer per row
The blank schedule is only useful if each row points to a real, identifiable asset. Serial numbers stop two identical switches in the same rack being confused. Naming the engineer per row makes it clear who owns the next visit, and it gives you a starting point when that engineer is on leave and the visit needs reassigning.
Choosing the right frequency: weekly to yearly
The template uses six frequency bands. They cover most AMC commitments.
- Weekly. For high-duty or business-critical equipment where a missed fault is expensive and the checks are quick: DG sets, critical cooling, anything the site runs on continuously.
- Monthly. A common AMC default for equipment with consumables or visible wear: UPS routine checks, CCTV recording verification, AC filters, firewall log and licence review.
- Quarterly. The other common AMC band, often used for network and server infrastructure where monthly visits would add cost without adding much insight.
- Half-yearly. For deeper checks on equipment that is otherwise visited more often (battery backup tests), or for low-duty assets.
- Yearly. For low-duty equipment, annual calibration or certification, and full audits of an installation.
- Custom (every N days). For intervals that don't fit a calendar band, such as every 45 or 60 days, usually because the OEM manual or the contract specifies them that way.
If you can't decide between two bands, check three things: what the OEM manual says, what the contract promises, and what the visit history shows. If the last few quarterly visits all found problems that had clearly been building for weeks, the interval is probably too long.
Monthly vs quarterly PM checklists: what changes
A quarterly checklist is usually the monthly checklist plus a set of deeper items. Here is a UPS example.
Monthly checklist
- Check alarm panel and event log
- Record input/output voltage and load
- Inspect batteries for swelling, leakage or corrosion
- Clean vents and filters
Quarterly checklist (monthly items, plus)
- Check battery terminal tightness
- Review firmware or controller version against the manufacturer's advisories
- Compare load against rated capacity and note headroom
- Review the event log for the whole quarter, not just since the last visit
The same pattern works for network equipment. Monthly covers status lights, logs and backups. Quarterly adds firmware review, a check of redundancy failover where the customer allows it, and a comparison of the running configuration against the documented baseline.
Where spreadsheet PM schedules break down
A spreadsheet is a perfectly good place to start, and the template above works in one. The problems tend to show up as the number of contracts, sites and engineers grows.
- Nothing flags an overdue visit unless someone builds it. A "Next due" column only helps if somebody looks at it and compares it with today's date. Conditional formatting can help, but it has to be maintained.
- The checklist gets retyped. The checklist lives in the template, while the engineer works from a job sheet, a WhatsApp message or memory. Every copy is a chance for items to drop off.
- The next due date doesn't move on its own. After a visit, someone has to update "Last visit" and "Next due". When that step is missed, the schedule quietly falls behind reality.
- The schedule isn't connected to the contract. The spreadsheet doesn't know when the AMC ends. Visits continue after expiry, or stop while the contract is still active.
- Visit evidence is scattered. Photos, readings and sign-offs end up in email threads and phone galleries, so they are hard to find when the customer asks for proof at renewal time.
None of this means the spreadsheet is wrong. It means the schedule needs to sit somewhere that holds the plan, the checklist and the visit record together.
Running the schedule in DexVee
In DexVee, each row of the template becomes a maintenance plan. A plan holds the frequency, using the same six bands as the template (weekly, monthly, quarterly, half-yearly, yearly, or a custom interval in days). It can be linked to the customer account, the asset and the AMC contract, and it can name the assigned engineer and a work order template that carries your checklist. The first due date is one interval after the plan's start date, and any active plan past its due date is flagged as overdue in the plans list, which also shows how many work orders each plan has generated.
When a visit is due, a coordinator generates the work order from the plan in one step. To be clear: visits are generated from the plan on demand, not automatically. The generated work order is a maintenance job for the plan's customer contact with the plan's engineer assigned, it links back to the plan, and the template's checklist is copied onto it, so the checklist you wrote in the template is exactly what the engineer ticks on site. The account, asset and contract are not copied from the plan to the work order, so check those on the work order if you need them there. At the same moment, the plan records the visit as its last run and rolls the next due date forward by one interval, counted from the day the work order was generated. Generating a visit late therefore pushes the following due date later too, so it is worth generating promptly when a plan comes due.
Each work order generated from a plan stays linked to it, and the engineer's service report on that work order is your evidence of service delivered when the contract comes up for renewal. Billable parts or services on a completed work order are drafted into an invoice in Finance, unless that automatic drafting is switched off in your settings (see AMC billing).
If you want to move this template off a spreadsheet, see how AMC maintenance scheduling works in DexVee, or explore the wider Field Service Management module.